Projects
Every project, its phase, status, and next important date.
|
Sep 10, 2026 - Sep 10, 2026
6N01-1086
ANL B203 AHU6-F1 Controls Upgrade
Argonne National Laboratory
Scope of Work Summary
Thomas to upgrade F1 AHU
Sep 9, 2026 · 4:17 AM·Wojciech
sdasfasdasfasdsada
Timeline
TODAY
Nov 3
Start: Jul 1
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
25d overdue
|
Sep 9, 2026 - Sep 9, 2026
6N01-1220
Building 369
Analytical Laboratory
Argonne National Laboratory
Scope of Work Summary
Provide building automation system engineering, commissioning, and project management to extend the existing Metasys system, including installing new BACnet field controllers for an exhaust fan, fume hood air valves, thermostats, and associated network cabling.
Sep 9, 2026 · 9:14 PM·Wojciech
Working on it
Timeline
TODAY
Nov 3
Start: Sep 7
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
1d overdue
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:29 AM·Wojciech
original by woj
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:28 AM·Cris G
edited by admin
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 9, 2026
6N01-1217
ANL B201 3rd Floor VAV boxes
Argonne National Laboratory
Scope of Work Summary
11 VAV boxes. — Status: Cris ordered material — Next: Universal starts 8/24/26 with 5 boxes. Need submittals Aug 25th (Cris)
Sep 7, 2026 · 6:02 PM·Cris G
Edited note — inline edit worked
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1191
B306 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Next: Adam and Colton working on submittals Aug 28th. Parts on order.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026
6N01-1162
ANL APS Sector 34 HVAC FPB
Argonne National Laboratory
Scope of Work Summary
(2X) FPB — Next: Have all the parts. Universal to start piping. Need submittals 8/28/26 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0996
ANL B201 NC-2 & NC -25
Argonne National Laboratory
Scope of Work Summary
PMI and GPL Logic
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0936
ANL B362 SMART LAB
Argonne National Laboratory
Scope of Work Summary
Project on IIS displayed on 1/5/26. Starting Project — Status: Waiting for customer to let us know when we can start — Next: Substential completion 8/31/2026. VFD Start Up 8/26/2026 Cx to be scheduled
Sep 7, 2026 · 5:45 PM·Cris G
Project is not working
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
ANL B362 High Bay AHU replacement-OPTION-3
Argonne National Laboratory
Scope of Work Summary
CO Option-2 ACOND-21 — Status: CO recieved. Need Submittals. Sept 14t 2026 (Adam)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-960
5N01-960
Argonne National Laboratory
Scope of Work Summary
B-213 CHW Sys — Next: Submittals for Change Order for B213. Should be ready on Sept 8th 2026 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-1000
ANL B200 Steam and Condensate replacement
Argonne National Laboratory
Scope of Work Summary
JCI to provide steam valve and do BACnet MS/TP integration. — Status: JCI provided control submittal and ordered valve. — Next: Waiting for valve to be shipped from ONICON. Scheduled for 11/6/2025.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
5N01-0910
B222-B223 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Universal to install stat for split system. Universal to install JCI stat and wire to closest controller. — Status: Pending start. Customer requested credit for not connecting ACC-1 to BAS. — Next: Waiting for customer to let us know when to start. Sent another email to GC. When JCI can install stat.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 8, 2026
5N01-0835
B362 Dynamometer
Argonne National Laboratory
Scope of Work Summary
Universal rough-in 8/15/25; WF to provide deductive CO; explain scope to customer — Status: Bul#5 CO issued. Deductive CO issued. JCI as far as we can go. Bul #7 CO received. — Next: Need as-built drawings. Aug 28th , 2026 (Cris). Customer training to be scheduled.
Sep 7, 2026 · 5:43 PM·Cris G
sadadsad
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1055
ANL 450 Chillers Upgrade PH-2
Argonne National Laboratory
Scope of Work Summary
Base Proposal_(3X) New HX Valves. Demo old ones and replace with new valves. New System Graphics. T&B and Cx. — Status: Valve submittals approved. Cris placed order. — Next: Valves are on site. Waiting for installation.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
4N01-0327
ANL 450 Chiller Replacement
Argonne National Laboratory
Scope of Work Summary
Base bid Ch-802, Option- 3 Ch-803, & Sand Filter. — Status: Demo is done. Sand filter integration is done. Parts ordered. Cris responded to all comments from the enginner of record. — Next: Complete. Cx done. 8-1 chiller BRAY Valve actuator was replaced replaced. Scott was on site RMA issued for two actuators. Issue with CH-803 flow meter.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
Show archived (24)
Projects
Every project, its phase, status, and next important date.
|
Sep 10, 2026 - Sep 10, 2026
6N01-1086
ANL B203 AHU6-F1 Controls Upgrade
Argonne National Laboratory
Scope of Work Summary
Thomas to upgrade F1 AHU
Sep 9, 2026 · 4:17 AM·Wojciech
sdasfasdasfasdsada
Timeline
TODAY
Nov 3
Start: Jul 1
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
25d overdue
|
Sep 9, 2026 - Sep 9, 2026
6N01-1220
Building 369
Analytical Laboratory
Argonne National Laboratory
Scope of Work Summary
Provide building automation system engineering, commissioning, and project management to extend the existing Metasys system, including installing new BACnet field controllers for an exhaust fan, fume hood air valves, thermostats, and associated network cabling.
Sep 9, 2026 · 9:14 PM·Wojciech
Working on it
Timeline
TODAY
Nov 3
Start: Sep 7
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
1d overdue
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:29 AM·Wojciech
original by woj
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:28 AM·Cris G
edited by admin
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 9, 2026
6N01-1217
ANL B201 3rd Floor VAV boxes
Argonne National Laboratory
Scope of Work Summary
11 VAV boxes. — Status: Cris ordered material — Next: Universal starts 8/24/26 with 5 boxes. Need submittals Aug 25th (Cris)
Sep 7, 2026 · 6:02 PM·Cris G
Edited note — inline edit worked
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1191
B306 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Next: Adam and Colton working on submittals Aug 28th. Parts on order.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026
6N01-1162
ANL APS Sector 34 HVAC FPB
Argonne National Laboratory
Scope of Work Summary
(2X) FPB — Next: Have all the parts. Universal to start piping. Need submittals 8/28/26 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0996
ANL B201 NC-2 & NC -25
Argonne National Laboratory
Scope of Work Summary
PMI and GPL Logic
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0936
ANL B362 SMART LAB
Argonne National Laboratory
Scope of Work Summary
Project on IIS displayed on 1/5/26. Starting Project — Status: Waiting for customer to let us know when we can start — Next: Substential completion 8/31/2026. VFD Start Up 8/26/2026 Cx to be scheduled
Sep 7, 2026 · 5:45 PM·Cris G
Project is not working
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
ANL B362 High Bay AHU replacement-OPTION-3
Argonne National Laboratory
Scope of Work Summary
CO Option-2 ACOND-21 — Status: CO recieved. Need Submittals. Sept 14t 2026 (Adam)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-960
5N01-960
Argonne National Laboratory
Scope of Work Summary
B-213 CHW Sys — Next: Submittals for Change Order for B213. Should be ready on Sept 8th 2026 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-1000
ANL B200 Steam and Condensate replacement
Argonne National Laboratory
Scope of Work Summary
JCI to provide steam valve and do BACnet MS/TP integration. — Status: JCI provided control submittal and ordered valve. — Next: Waiting for valve to be shipped from ONICON. Scheduled for 11/6/2025.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
5N01-0910
B222-B223 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Universal to install stat for split system. Universal to install JCI stat and wire to closest controller. — Status: Pending start. Customer requested credit for not connecting ACC-1 to BAS. — Next: Waiting for customer to let us know when to start. Sent another email to GC. When JCI can install stat.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 8, 2026
5N01-0835
B362 Dynamometer
Argonne National Laboratory
Scope of Work Summary
Universal rough-in 8/15/25; WF to provide deductive CO; explain scope to customer — Status: Bul#5 CO issued. Deductive CO issued. JCI as far as we can go. Bul #7 CO received. — Next: Need as-built drawings. Aug 28th , 2026 (Cris). Customer training to be scheduled.
Sep 7, 2026 · 5:43 PM·Cris G
sadadsad
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1055
ANL 450 Chillers Upgrade PH-2
Argonne National Laboratory
Scope of Work Summary
Base Proposal_(3X) New HX Valves. Demo old ones and replace with new valves. New System Graphics. T&B and Cx. — Status: Valve submittals approved. Cris placed order. — Next: Valves are on site. Waiting for installation.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
4N01-0327
ANL 450 Chiller Replacement
Argonne National Laboratory
Scope of Work Summary
Base bid Ch-802, Option- 3 Ch-803, & Sand Filter. — Status: Demo is done. Sand filter integration is done. Parts ordered. Cris responded to all comments from the enginner of record. — Next: Complete. Cx done. 8-1 chiller BRAY Valve actuator was replaced replaced. Scott was on site RMA issued for two actuators. Issue with CH-803 flow meter.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
Show archived (24)
ORBITAL
Projects
Every project, its phase, status, and next important date.
|
Sep 10, 2026 - Sep 10, 2026
6N01-1086
ANL B203 AHU6-F1 Controls Upgrade
Argonne National Laboratory
Scope of Work Summary
Thomas to upgrade F1 AHU
Sep 9, 2026 · 4:17 AM·Wojciech
sdasfasdasfasdsada
Timeline
TODAY
Nov 3
Start: Jul 1
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
25d overdue
|
Sep 9, 2026 - Sep 9, 2026
6N01-1220
Building 369
Analytical Laboratory
Argonne National Laboratory
Scope of Work Summary
Provide building automation system engineering, commissioning, and project management to extend the existing Metasys system, including installing new BACnet field controllers for an exhaust fan, fume hood air valves, thermostats, and associated network cabling.
Sep 9, 2026 · 9:14 PM·Wojciech
Working on it
Timeline
TODAY
Nov 3
Start: Sep 7
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
1d overdue
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:29 AM·Wojciech
original by woj
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
TEST Attribution Verify
Test Site
Scope of Work Summary
Sep 9, 2026 · 4:28 AM·Cris G
edited by admin
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 9, 2026
6N01-1217
ANL B201 3rd Floor VAV boxes
Argonne National Laboratory
Scope of Work Summary
11 VAV boxes. — Status: Cris ordered material — Next: Universal starts 8/24/26 with 5 boxes. Need submittals Aug 25th (Cris)
Sep 7, 2026 · 6:02 PM·Cris G
Edited note — inline edit worked
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1191
B306 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Next: Adam and Colton working on submittals Aug 28th. Parts on order.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026
6N01-1162
ANL APS Sector 34 HVAC FPB
Argonne National Laboratory
Scope of Work Summary
(2X) FPB — Next: Have all the parts. Universal to start piping. Need submittals 8/28/26 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0996
ANL B201 NC-2 & NC -25
Argonne National Laboratory
Scope of Work Summary
PMI and GPL Logic
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
6N01-0936
ANL B362 SMART LAB
Argonne National Laboratory
Scope of Work Summary
Project on IIS displayed on 1/5/26. Starting Project — Status: Waiting for customer to let us know when we can start — Next: Substential completion 8/31/2026. VFD Start Up 8/26/2026 Cx to be scheduled
Sep 7, 2026 · 5:45 PM·Cris G
Project is not working
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
ANL B362 High Bay AHU replacement-OPTION-3
Argonne National Laboratory
Scope of Work Summary
CO Option-2 ACOND-21 — Status: CO recieved. Need Submittals. Sept 14t 2026 (Adam)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-960
5N01-960
Argonne National Laboratory
Scope of Work Summary
B-213 CHW Sys — Next: Submittals for Change Order for B213. Should be ready on Sept 8th 2026 (Cris)
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
5N01-1000
ANL B200 Steam and Condensate replacement
Argonne National Laboratory
Scope of Work Summary
JCI to provide steam valve and do BACnet MS/TP integration. — Status: JCI provided control submittal and ordered valve. — Next: Waiting for valve to be shipped from ONICON. Scheduled for 11/6/2025.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
5N01-0910
B222-B223 Elevator Modernization
Argonne National Laboratory
Scope of Work Summary
Universal to install stat for split system. Universal to install JCI stat and wire to closest controller. — Status: Pending start. Customer requested credit for not connecting ACC-1 to BAS. — Next: Waiting for customer to let us know when to start. Sent another email to GC. When JCI can install stat.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 8, 2026
5N01-0835
B362 Dynamometer
Argonne National Laboratory
Scope of Work Summary
Universal rough-in 8/15/25; WF to provide deductive CO; explain scope to customer — Status: Bul#5 CO issued. Deductive CO issued. JCI as far as we can go. Bul #7 CO received. — Next: Need as-built drawings. Aug 28th , 2026 (Cris). Customer training to be scheduled.
Sep 7, 2026 · 5:43 PM·Cris G
sadadsad
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
6N01-1055
ANL 450 Chillers Upgrade PH-2
Argonne National Laboratory
Scope of Work Summary
Base Proposal_(3X) New HX Valves. Demo old ones and replace with new valves. New System Graphics. T&B and Cx. — Status: Valve submittals approved. Cris placed order. — Next: Valves are on site. Waiting for installation.
Timeline
No target date
Solution Navigator
IIS - Contract Cost Review
Scope of Work
Mechanical
Target Date
|
Sep 7, 2026 - Sep 7, 2026
4N01-0327
ANL 450 Chiller Replacement
Argonne National Laboratory
Scope of Work Summary
Base bid Ch-802, Option- 3 Ch-803, & Sand Filter. — Status: Demo is done. Sand filter integration is done. Parts ordered. Cris responded to all comments from the enginner of record. — Next: Complete. Cx done. 8-1 chiller BRAY Valve actuator was replaced replaced. Scott was on site RMA issued for two actuators. Issue with CH-803 flow meter.